How will this impact river use on the Roaring Fork?

The City intends to limit river closures with adequate notification. Most full closures will take place overnight, excluding the full closure for the bridge replacement. Temporary holds may be necessary during critical overhead work and during the in-water dates (August 15 – October 15) when the piers are being removed from the river.  Please reach out to City staff with any concerns. The City intends to keep full contact with the River Users during this project and hope to minimize our impacts.

Show All Answers

1. What is the project schedule?
2. What traffic impacts will I see as a commuter?
3. How will this impact river use on the Roaring Fork?
4. Why isn't South Bridge being built before the 27th Street Bridge replacement?
5. How much traffic goes over the bridge?
6. How much will this project cost?
7. What is a pier?
8. What is an abutment?
9. What is a micropile?
10. What is a soil nail?