Soil nail walls are now complete on both the east and west sides of the bridge. Crews have now shifted focus to micropile construction which essentially make up the new bridge abutments.
Know Before You Go: Thursday 4/11 and Friday 4/12
- It is anticipated that ongoing lane closures on the 27th Street Bridge will extend from the normal off-peak through the afternoon peak on Thursday and Friday.
- Delays anticipated. Please allow extra travel time through the area and do not block intersections.
Bus Stop Service Reminder:
The 27th Street/S. Grand Ave. Ride Glenwood bus stop will close until further notice on Monday, April 22 with the spring schedule change. Service will be relocated to the 27th BRT station on CO-82. This stop will be closed for the duration of project construction. The last day of service at this location will be Sunday, April 21.
Tips for Motorists:
Plan extra travel time through the area especially during peak times. Delays have ranged between approximately 5 and 25 minutes and are intermittent in nature.
Use alternate routes (CO-82). Midland Avenue should be used for local traffic only.
Walk, bike and carpool whenever possible. The fewer cars trying to get through the area will mean shorter delays.
Do not block the roundabout and follow flagger instructions. This helps to keep traffic flowing.
All work is weather dependent and subject to change based on conditions encountered.
Project Information:
If you have any questions or concerns, please reach out to the project team.
Project Webpage: cogs.us/27thStreetBridge -- AND/OR -- cogs.us/SunlightBridge
Email: 27thStreetBridge@gmail.com