South Midland crews will be paving on Monday, May 9. Paving operations were extended due to weather and project conditions. The majority of project paving will be complete after Monday, May 9. There will still be minor paving select areas through the end of the project as we continue to work towards closing out key areas throughout the corridor. We are all excited to see paving operations wrapping up.
Traffic delays due to paving are still expected during work hours: 9 a.m. – 3 p.m., Wednesdays from 9 a.m. – 2 p.m., and Saturdays from 8 a.m. – 5 p.m.
New for next week: Atkinson trailhead parking lot closure May 9 - May 13
The parking lot serving the Atkinson trailhead will be temporarily closed for parking throughout the week. Crews will be working in this area for construction staging and paving. Alternate routes for Atkinson Trail are Old Cardiff Bridge or Midland Ave.
Upcoming scope of work:
Beginning next week motorists will start to see the installation of the final sculpted facing on the uphill shotcrete walls.
Know before you go by signing up for South Midland email or text alerts at cogs.us/NotifyMe
PROJECT INFORMATION | INFORMACIÓN SOBRE EL PROYECTO
Phone (call or text) | Teléfono (llamar o por texto): 970-618-5379
Email: southmidlandproject@gmail.com
Webpage | Sitio web: cogs.us/SouthMidland
#KeepSouthMidlandMoving